The City of Burlington is building an addition to the new playground at Central Park (2299 New St.) in Spring-Summer 2022.
The proposed improvements include:
The park playground (behind library) will remain open during construction, however, there will be some minor disruptions due to construction activity. The new accessible swing area will be closed and fenced off with signs posted until final safety inspection is complete. Thank you in advance for your cooperation during construction.
(colours may vary)
Project Milestone |
Timing |
Design work |
Complete |
Burlington City Council approval of 2022 capital budget |
Dec. 15, 2021 |
Tender for a construction contractor |
April - May 2022 |
Construction begins |
May-June 2022 |
Completion of construction |
August-October 2022* |
*due to the COVID-19 pandemic and the production and service delays in the construction industry, this completion date may be affected.