The City of Burlington and Halton Region will be continuing improvements in the Autumn Hill Crescent area and on Palmer Drive in 2022. This will include curb, sidewalk, and asphalt replacement, street lighting upgrades (City), and full watermain and water service replacement (Region) on the streets per the map below.
The City of Burlington and Halton Region will be working on:
Location | City Works | Region Works |
---|---|---|
Palmer Drive – Guelph Ln. to Michael Cr. |
|
Full watermain and water service replacement. |
Palmer Drive – Michael Cr. to Centennial Dr. |
|
Full watermain and water service replacement. |
Autumn Hill Cr. – Driftwood Dr. to Snowhill Ct. Driftwood Dr. – Autumn Hill Cr. to Hemlock Ct. |
|
Full watermain and water service replacement. |
Carncastle Gt. Flanagan Ct. Parknoll Ct. Fontana Ct. Driftwood Dr. – Autumn Hill Cr. to dead-end |
|
|
Driftwood Dr. - Hemlock Ct. to Autumn Hill Cr. Autumn Hill Cr. - Snowhill Ct. to Driftwood Dr. Hemlock Ct. Snowhill Ct. |
|
The construction timeline for the above-mentioned streets – Mid-April to December 2022
Inquiry | Contact |
---|---|
Day-to-day construction |
Tom Georgiadis, Construction Inspector City of Burlington 905-220-1693 |
Watermain and service replacement |
Gurpreet Chaggar, Project Manager II Halton Region 905-825-6000, ext. 3059 |
All other construction inquiries |
Ryan Stoneman, Project Manager City of Burlington 905-335-7600, ext. 7818 |
Information for Homeowners |
ParkingDuring normal construction hours, Monday to Friday, 7 a.m. to 5:30 p.m., vehicle access to and from your property may be difficult. Driveways may be temporarily closed when work is being carried out in the immediate area. When your driveway is inaccessible or closed, please park on a neighbouring street, or where no construction is taking place. If your vehicle will be in contradiction to the below by-law, register your vehicle for the On-Street Parking Exemption Program at: How does a parking exemption work? It allows a vehicle to park on the street beyond the 5-hour limit or overnight between 1 a.m. to 6 a.m., up to 15 days per calendar year, per license plate. The only two parking offences waived AFTER a vehicle is registered for a parking exemption are: 1. park exceeding 5-hour limit All other parking offences apply as they are not part of the parking exemption program. If you have any questions about parking, please contact Parking Services at 905-335-7816. Garbage Pickup Please continue to put your garbage and recycling out on the usual day. It is the contractor's responsibility to move your garbage to a location that can be easily picked up by the garbage truck and return your garbage containers. To help the contractor return your bins to you, we ask that you write your house number on your garbage cans, recycling bins and green carts. Access to Your Home During normal construction hours, Monday to Friday, 7 a.m. to 5:30 p.m., vehicle access to and from your property may be difficult, and driveways may be temporarily closed when work is being carried out in the immediate area. The construction inspector or contractor will notify you of this before the closure. Water Services As with any project of this nature, there may be some disruptions to water services at times throughout the construction. You will be given a minimum of 48 hours notice before any scheduled water shut down. Thank you for your patience. Vibration There may be times when you feel some minor vibrations from construction equipment. We recommend that you remove small, light objects from shelving around the house to prevent damage. Lawn Irrigation System If you have a lawn irrigation system, we recommend that you disconnect and remove any sprinkler heads within the city's road allowance. The city inspector will notify you if your system is affected. Road Closures/Lane Restrictions Lane restrictions and short-term road closures will be in place during construction. You will still have access to your home. Additional information will be provided during construction. Canada PostDue to access concerns regarding mail delivery, single-point mail pick-up locations will be arranged by Canada Post. Driveway RestorationUnder the contract, asphalt/concrete driveways adjacent to new curb and sidewalk, or that contain water service shutoffs, will be restored from the limit of disturbance to the curb line at the roadway. Option A
Option B
If Option B is your preference, please contact Hasan Rabby at hasan.rabby@burlington.ca by July 31, 2022. |
Updates will be posted throughout the project.