Construction activity will commence the week of April 27, 2020 and proceed as detailed below. Please note that this construction schedule is tentative and subject to change:
Location |
Work being done |
Estimated to be complete |
Coldstream Drive |
Streetlighting upgrades |
End of September 2020 |
Driveways and sod restoration |
Middle of September 2020 |
|
Pave top layer of asphalt |
Spring of 2021 |
|
Manchester Drive Leominster Drive Middlesmoor Crescent Sherburne Drive
|
Driveways and sod restoration |
End of September 2020 |
Pave top layer of asphalt |
Beginning of October 2020 |
Inquiry/Concern |
Name |
Contact |
Day-to-day construction inquiries |
Mark Sartor Construction Inspector City of Burlington |
905-815-3082 |
Watermain inquires |
Rama Garigipati Project Manager II Halton Region |
905-825-6000, Ext. 7256 |
All other construction inquiries |
Hasan Rabby Contract Administrator City of Burlington |
905-335-7600, ext. 7507 |
All other construction inquiries |
Janine Yaromich, P.Eng Project Manager City of Burlington |
905-335-7600, ext. 7421 |
Information for Homeowners |
ParkingDuring construction, the five-hour maximum limit for street parking will not apply when your driveway is inaccessible or closed. In this situation, please park on neighbouring streets, were there is no construction. Please do not:
Please do obey all parking regulations to make sure you don’t get a ticket. If you have any questions about parking, please contact Parking Services at 905-335-7816. Garbage PickupPlease continue to put your garbage and recycling out on the usual day. It is the contractors' responsibility to move your garbage to a location that can be easily picked up by the garbage truck and return your garbage containers. To help the contractor return your bins to you, we ask that you write your house number on your garbage cans, recycling bins and green carts. Access to Your HomeDuring normal construction hours, Monday to Friday, 7 a.m. to 5:30 p.m., vehicle access to and from your property may be difficult, and driveways may be temporarily closed when work is being carried out in the immediate area. The inspector or contractor will notify you of this before the closure.
VibrationThere may be times when you feel some minor vibrations from construction equipment. We recommend that you remove small, light objects from shelving around the house to prevent damage. Lawn Irrigation SystemIf you have a lawn irrigation system, we recommend that you disconnect and remove any sprinkler heads within the city's road allowance. The city inspector will notify you if your system is affected.
|
Project Updates |