Applying for a Building Permit

Learn how to apply for a building permit in Burlington, including application steps, required documents, electronic submissions, fees and permit inspections.

You can apply to the City of Burlington for a new building permit or re-submit if you have an existing building permit.

Building permits make sure your project is built to the minimum standards set out in the Ontario Building Code and ensure compliance with the City's Official Plan, Building Permit By-law 030-2026, as amended.

How to apply for a new building permit

See these steps to learn how to apply for a new building permit.


1. Review requirements for your site plan, property zoning, and grading and drainage

Make sure you have the necessary approvals and clearances for your site plan, zoning, and grading and drainage. You must have these approvals and clearances before you can apply for a building permit.

2. Review our Electronic Application Submission Standards

We only accept building permit applications through electronic submission. Review our Electronic Building Permit Application Submission Standards.

These standards outline how to prepare your digital drawings and documents for submission. We do not accept submissions that do not meet these standards.

If you have sent insufficient documents, you will need to re-submit your documents before your application is accepted.

3. Review project-specific building permit application requirements

Review the project-specific application checklist that applies to your project. You can find the list of application submission requirements on this page below.

You must include all required items from the checklist in your submission package.

4. Complete the Building Permit Application and gather your application requirements

Complete the Building Permit Application Form. Gather and complete any additional requirements applicable from Step 2.

5. Submit your building permit application package

Send your completed building permit application package to us by email. In the subject line, please state “Building Permit Application” followed by the project address, including suite/unit number if applicable.

If your package is more than 20 MB, please email us to request a large file transfer.

Example subject line: Building Permit Application - 123 Main St., Unit 7

6. Receive a response from the City

We will email you to let you of next steps for your application. This includes the associated permit fee and how to pay if your application is successful.

We will let you know of any questions, if we need more information or if you need to re-submit if the documents are insufficient.

7. Pay the associated building permit fee

Follow the instructions set out in our email to pay your building permit fee. Please pay your fee within two days of our response.

8. Receive your building permit and arrange for project inspections

We will issue you your building permit once all requirements are completed and fees are paid. Learn how you can book any associated inspections with your permit.

Re-submissions to existing permit applications

If you need to re-submit a package for your existing permit application, please follow the same steps as you would for a new application . When you are ready to submit, in the subject line of your email, please state "Building Permit Re-submission" followed by the application number and project address, including suite/unit number if applicable. If your package is more than 20 MB, please email us to request a large file transfer.

  • Example subject line: Building Permit Re-submission - 21-123456 - 123 Main St., Unit 7

Project-specific application requirements

View the project-specific building permit application requirements and supplementary documents and forms for:

Check the status of a permit

Check the status of an issued building permit in Burlington using our interactive permit map. Find active permits dating back to five years, assigned inspectors and contact information.