Appleby Creek Flood Mitigation Municipal Class Environmental Assessment - Addendum

The Appleby Creek Flood Mitigation Municipal Class Environmental Assessment (ACFMEA) Study was completed in February 2019. The ACFMEA study evaluated alternative solutions along Appleby Creek, from New Street to the GO Transit Rail corridor (near Appleby Go Train Station), to identify specific opportunities to reduce flooding risk and protect the natural heritage features and functions within the study corridor.

The ACFMEA recommended preferred solutions for three flood-vulnerable areas within the study corridor.

Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.

Project scope

For the study area north of Fairview Street (Reach 3), three options were assessed to reduce the extent of the flood hazard:

  • Option 1 - Do Nothing
  • Option 2 - Replace the existing bridge (Fairview Street) with a 17-metre span to convey the 100-year storm.
  • Option 3 - Replace the existing bridge with a span large enough to pass the Regional Storm

Option 2 was originally selected as the preferred alternative however, the ACFMEA File Report acknowledges that this option still results in the flooding of private property and the overtopping of Fairview Street under Regional Storm conditions. Option 2 was selected over Option 3 primarily due to the concerns of the capital cost at the time of evaluation.

Since the completion of the ACFMEA, the socio-cultural and economic environments of the study area have changed as a result of plans for land use intensification and proposed development within the vicinity of the Fairview Street crossing. As a result, the preferred solution identified in the ACFMEA for the Fairview Street crossing structure does not adequately address the flooding risks within the flood limits of adjacent development lands, specifically development lands known as Oval Court lands.

As such, the purpose of this Addendum process is to address the change of the preferred solution. The Addendum report will identify the circumstances necessitating the change to the larger hydraulic structure, and the potential environmental impacts and provide a comprehensive list of mitigative measures.

R.J. Burnside & Associates Limited (Burnside) was retained by Branthaven Development Corporation to complete an addendum to the Appleby Creek Flood Mitigation Municipal Class Environmental Assessment (ACFMEA) completed by Aquafor Beech Limited for the City of Burlington in February 2019.

Public engagement

A Public Open House is planned to provide information about the project, gather and respond to public comments. Representatives of the project team will be available to discuss the Addendum and answer questions.

Project contacts

To provide comments on the project or if you require alternative accommodations to view the Addendum, please contact either of the following Project Team members

Philip A. Rowe, C.E.T., EP.

Consultant Project Manager

R.J. Burnside & Associates Limited

1266 South Service Road, Suite C2

Stoney Creek ON L8E 5R9

Phone: 905-821-5915

Email Philip Rowe


Arif Shahzad, M.Eng., P.Eng.

Stormwater Engineer - Capital

City of Burlington

426 Brant Street, P.O. Box 5013

Burlington ON L7R 3Z6

Phone: 905-335-7600 ext. 7486

Email Arif Shahzad

Documents, reports, and updates

Updates will be posted throughout the project.

Subscribe Back to Environmental Assessments Projects

Contact Us


Design and Construction - Requirements
426 Brant St., PO Box 5013
Burlington, ONĀ  L7R 3Z6

Phone: 905-335-7777
Email Design and Construction - Requirements