Work on the cherry tree and pathway renewal is progressing according to plan and schedule.
Construction of the new pathway is expected to begin Monday, Sept. 28 and be completed by the end of the fall, 2026.
Site preparation, including removal of select invasive and/or declining trees (including Tree of Heaven, mulberry and Norway maple) will begin Oct. 7, after a bird nest assessment is done to confirm there are no active nests present. The cherry trees will remain.
The park will stay open during the tree removals and construction period. Only the impacted areas will be closed with fencing. For your safety, please stay clear of the working areas.
These are the first real, visible steps to ensuring the beauty and legacy of the Spencer Smith Park cherry trees and pathway.
| Project Description |
Expected Timeline |
|
Project tender and award process
|
Summer 2026
|
|
New pathway construction
|
Fall 2026
|
|
Planting of new cherry trees
|
Spring 2027
|
Phase 2
The second phase will begin in 2031 and include the reconstruction of the existing pathway as well as cherry tree removals and replacements.
| Project Description |
Expected Timeline |
|
Removal of existing cherry trees and replacement with new cherry trees
|
2031
|
|
Renewal of existing pathway
|
2031
|
Note: The construction schedule outlined is tentative. Delays and schedule changes may occur throughout the course of the project.