Spencer Smith Park Water Jet Plaza Improvements

calendar icon

Construction Schedule

Late-October 2024

The City of Burlington is renewing Spencer Smith Park.

Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.

Proposed Improvements

This project includes:

  • New artificial turf
  • New concrete pad

What to expect during construction

Your safety during construction is our priority. 

The park will remain open. The water jet plaza will be closed during construction. A security fence will be in place to secure this area.

Do not enter the construction site at any time.

Next steps

Project Milestone

Timing

Burlington City Council approval of 2024 Capital Budget

Completed, January 2024

Design Work

Completed, November 2023

Tender for construction contract

Completed, February 2024

Expected start of construction

September 30, 2024

Expected construction completion

October 23, 2024

Project contact

For more information about park design and construction, please contact:

Nick Pirzas
Supervisor, Engineering services
Email Nick Pirzas 

Subscribe Back to Park Renewal Projects

Contact Us


City of Burlington
426 Brant St., PO Box 5013,
Burlington, ON  L7R 3Z6

Phone: 905-335-7777
Toll Free: 1-877-213-3609
Email: city@burlington.ca