Windows-to-the-Lake

calendar icon

Construction schedule

2023 to 2024

Windows-to-the-Lake are small park settings along the shoreline, connecting Burlington residents to Lake Ontario. They are a place to meet, take a rest, observe nature, listen to the waves, watch weather move across the water, and enjoy the beauty of sunsets over the lake.

The City will be enhancing these connections to the water over the next two years.  Each site renewal will provide, at minimum, a paved pathway and accessible seating.

Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.

Project scope and schedule

Design and construction of lake property by location:

Appleby Place

  • 2022-2023 – Design of shoreline reconstruction, design of parkland/window-to-the-lake
  • July 2024 – Start of shoreline construction, followed by construction of parkland/window-to-the-lake
  • December 2024 – Expected construction completion

The project will include:

  • Tree removals on slope to lake (completed in February 2024)
  • Shoreline reconstruction
  • Removal of existing light standard
  • Permeable pavement service area around existing forcemain utility area
  • Concrete walkways
  • Accessible ramp entrance
  • New thin profile retaining wall adjacent to proposed ramp, to protect existing black locust trees
  • Decorative pedestrian guard at top of lake bank
  • Park I.D. sign and interpretive signage
  • Site furnishings – benches, waste receptacle, bike rack, bollards
  • Trees, shrubs and planting bed

View Appleby Place concept plan image (PDF)

Green Street

  • 2021 – Design of shoreline reconstruction
  • 2022-2023 – Shoreline construction, design of parkland/window-to-the-lake
  • Spring-Fall, 2025 – Construction of parkland/window-to-the-lake

View the Green Street concept plan image (PDF)

Walkers Line

The City of Burlington is renewing the Walkers Line Window to the Lake.

  • 2022 – Shoreline assessment, design of parkland/window-to-the-lake
  • 2023 – Construction of parkland/window-to-the-lake
  • October 2023 – Start of construction
  • February 2024 – Construction complete – open to the public

View Walkers Line concept plan image (PDF)

Contact

Kim Napier
Landscape Architect
Parks Design and Construction, Engineering Services
Email Kim Napier

Subscribe Back to Park Renewal Projects

Contact Us


City of Burlington
426 Brant St., PO Box 5013,
Burlington, ON  L7R 3Z6

Phone: 905-335-7777
Toll Free: 1-877-213-3609
Email: city@burlington.ca