Havendale Boulevard Minor Reconstruction
City of Burlington portion of this reconstruction project is complete. Halton Region has some limited sanitary sewer repair works, which will include a road closure of Havendale Boulevard between Abbey Court and Rosseau Place, beginning Tuesday, Aug. 4 until Friday, Aug. 7. Please refer to the linked Project Update notification.
The City of Burlington and Halton Region will be making improvements in the Havendale Boulevard area between 2024 and 2025. Halton Region will be replacing the existing watermain and water services. The City will be replacing the roadway asphalt, replacing isolated areas of curb and sidewalk, performing minor storm sewer repairs, and installing streetlighting upgrades.
Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.
Online Public Information Centre (PIC)
Thank you to everyone who participated in the online Public Information Centre on March 07, 2024. Information from the PIC is available in the documents, reports and updates section.
Construction Schedule
End of June 2024 to December 2025
Project scope
The City of Burlington and Halton Region will be working on:
| Location | City Works | Region Works |
|
Havendale Boulevard (From Brant Street to cul-de-sac north of Monmouth Drive) |
|
|
|
Dawlish Road and Brant Street intersection (incl. approx. 25m east of Dawlish Road) |
|
|
Project schedule
The construction timeline for the above-mentioned streets is:
- End of June 2024 to December 2025.
Day-to-day construction inquiries
Watermain and service replacement
Patrick Wilkon,
Project Manager
Halton Region
905-825-6000, ext. 3402
Email Patrick Wilkon
All other construction inquiries
Chris Onishi
Project Manager
Tel. 905-335-7600, ext.7682
Email Chris Onishi
Information for homeowners
The following information may be helpful if you are concerned about a construction project in your neighbourhood.
There will be interruptions to your water service during construction while completing watermain tie-ins and when transferring the houses to the new watermain. Halton Region will provide 48 hours advanced notice of all scheduled service interruptions.
Some watermain installation and tie-in work may be required to take place at night.
As part of this project, the curb and sidewalks will be replaced. Minor regrading of your boulevard lawn near the road will be required. Any damage to your lawn, walkways, and driveways will be restored.
Road closures/lane restrictions
Lane restrictions and short-term road closures will be in place during construction. You will still have access to your home. Additional information will be provided during construction.
For the duration of construction, enforcement of the “5-Hour” maximum on-street parking by-law will be relaxed when your driveway is inaccessible or closed. Residents are asked to register their vehicle online or call 905-335-7816 Monday to Friday 8:30 to 4:30 p.m.
Vehicles are not permitted to park where signs are posted. (e.g. No Parking, No Stopping, and Fire Route etc.) In addition, vehicles are not to block fire hydrants, driveway access or park their vehicles facing the wrong direction.
How does a parking exemption work?
It allows a vehicle to park on the street beyond the five-hour limit or overnight between 1 a.m. and 6 a.m., up to 15 days per calendar year, per licence plate.
The only two parking offences waived after a vehicle is registered for a parking exemption are:
- Park exceeding five-hour limit
- Park between 1 a.m. and 6 a.m.
All other parking offences apply as they are not part of the parking exemption program.
During city construction projects, the extra days will not be included in the 15-day-per-year limit when your driveway is not accessible. However, it is important to register your vehicle for this program so that you will not receive a parking ticket.
If you have any questions as it relates to parking please contact Parking Services at
905-335-7816 during business hours (8:30 a.m. to 4:30 p.m., Monday to Friday).
You may at times experience some minor vibration from construction equipment. We recommend that you remove small light objects from shelving around the house.
If you require more details, please do not hesitate in calling the contacts above.
Tree protection barriers will be erected around all trees in the right-of-way, within the construction limits, with an opening to allow homeowner access to maintain the area within.
There will be a number of boulevard trees removed due to conflict with the installation of the new watermain. Alternate watermain installation locations and methods have been reviewed in depth, but it has been determined that these removals are unavoidable. Homeowners adjacent to these removals will each be informed prior to removal. The specific trees that require removal can be viewed on the project drawings on the project updates below.
If additional trees require removal due to unforeseen impact or conflict, homeowners will informed.
July 2026
- Havendale Boulevard Minor Reconstruction - Sanitary - July 2026 (PDF)
Updated PIC Drawings for current scope of work:
- PIC Drawings - All Streets - May 7, 2024 (PDF)
- PIC Drawings - Havendale (Brant Street to Fairchild Blvd) - May 7, 2024 (PDF)
- PIC Drawings - Havendale (Belgrave Ct to Winchester Ct) - May 7, 2024 (PDF)
- PIC Drawings - Havendale (Winchester Ct to Knights Bridge Ct) - May 7, 2024 (PDF)
- PIC Drawings - Havendale (Abbey Ct to Rousseau Pl) - May 7, 2024 (PDF)
- PIC Drawings - Havendale (Upper Middle to Cul de sac) - May 7, 2024 (PDF)
- PIC Presentation - March 7, 2024 (PDF)