New Street Bridge Replacement at Tuck Creek

The City of Burlington will be continuing improvements on New Street at Tuck Creek. This will include the replacement of the New Street Bridge at Tuck Creek, road resurfacing, and storm water culvert replacement.

calendar icon

Construction Schedule

June 2025 to November 2026

Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.

Project scope and schedule

Construction activity detailed below. Please note that this construction schedule is tentative and subject to change. 

  • Replacement of the bridge
  • Storm water management improvements
  • Road resurfacing

Schedule: June 2025 to November 2026

Note: During bridge construction, traffic will be staged allow the work to occur while maintaining vehicle flow in both directions.

Traffic impacts

During bridge construction, traffic will be staged allow the work to occur while maintaining vehicle flow in both directions. Lane reductions are anticipated on New Street within the project area. A single lane in each direction will be maintained for vehicle travel.

Residents and commuting traffic are urged to plan alternative routes or to allow for longer than regular travel times throughout the duration of the project.

Pedestrian detour routes will be maintained throughout the entirety of the project. The detour routes will have clear signage installed and will provide an alternative path around the construction work area.

Contacts

Day-to-day construction:

Tom Georgiadis, Construction Inspector
City of Burlington
905-220-1693
Email Tom Georgiadis

All other construction inquiries:

Chris Onishi , Project Manager
City of Burlington
905-335-7600, ext. 7682
Email Chris Onishi 

Nathan Youngs, Contract Administrator
City of Burlington
289-208-2468
Email Nathan Youngs

Information for homeowners

The following information may be helpful If you are concerned about a construction project in your neighbourhood.

Docoument, reports and updates

Updates will be posted throughout the project.

Subscribe Back to Road and Transportation Construction Projects

Contact Us


Design and Construction - Roadways
426 Brant St., PO Box 5013
Burlington, ON  L7R 3Z6

Phone: 905-335-7777
Email Design and Construction - Roadways