New Street Watermain Replacement at Tuck Creek
The City of Burlington will be making improvements to the watermain located on New Street at Tuck Creek. This advanced watermain work is needed to lower the watermain for future bridge work. The work is anticipated to begin in November in 2024 and be complete in May 2025.
Construction Schedule
November 2024 to May 2025
Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.
Project scope
The City of Burlington will be working on:
- Watermain installation (New Street between Woodview Road to Elwood Road)
Project schedule
The construction timeline for the above-mentioned streets is:
- November 2024 to May 2025.
Contacts
Day-to-day construction inquiries
All other construction inquiries
Chris Onishi
Project Manager
Tel. 905-335-7777, ext.7682
Email Chris Onishi
Information for homeowners
The following information may be helpful if you are concerned about a construction project in your neighbourhood.
Utilities such as Union Gas, Hydro and Bell Canada have already started to locate their existing infrastructure to prepare for this construction.
Please do not remove these marker stakes or paint markings. Staff will return to remove them once the project is complete.
There will be interruptions to your water service during construction while completing watermain tie-ins and when transferring the houses to the new watermain. Halton Region will provide 48 hours advanced notice of all scheduled service interruptions.
Some watermain installation and tie-in work may be required to take place at night.Local access and sidewalk closures
As part of this project, sections of sidewalk will be closed on the north side of New Street between Woodview Road and Elwood Road in order to maintain safety around the project area. Pedestrians are encouraged to utilize the detour route around the construction area.
The detour route is available below.
Road closures / lane restrictions
For the duration of construction, enforcement of the “5-Hour” maximum on-street parking by-law will be relaxed when your driveway is inaccessible or closed. Residents are asked to register their vehicle online on our Parking page or call 905-335-7816 Monday to Friday 8:30 to 4:30 p.m.
Vehicles are not permitted to park where signs are posted. (e.g. No Parking, No Stopping, and Fire Route etc.) In addition, vehicles are not to block fire hydrants, driveway access or park their vehicles facing the wrong direction.
How does a parking exemption work?
- It allows a vehicle to park on the street beyond the five-hour limit or overnight between 1 a.m. and 6 a.m., up to 15 days per calendar year, per licence plate.
- The only two parking offences waived AFTER a vehicle is registered for a parking exemption are:
- Park exceeding five-hour limit
- Park between 1 a.m. and 6 a.m.
- All other parking offences apply as they are not part of the parking exemption program.
During city construction projects, the extra days will not be included in the 15-day-per-year limit when your driveway is not accessible. However, it is important to register your vehicle for this program so that you will not receive a parking ticket.
If you have any questions as it relates to parking please contact Parking Services at
905-335-7816 during business hours (8:30 a.m. to 4:30 p.m., Monday to Friday).
You may at times experience some minor vibration from construction equipment. We recommend that you remove small, light objects from shelving around the house.
If you require more details, please do not hesitate in calling the contacts above.Tree protection barriers will be erected around all trees in the right-of-way, within the construction limits, with an opening to allow homeowner access to maintain the area within.
Documents, reports, and updates
Updates will be posted throughout the project.
- ES-24-24 Pedestrian Detour Route (PDF) - Oct. 30, 2024
- ES-24-24 Watermain Installation – General Arrangement (PDF) - Oct. 30, 2024