Rob McQueen, Construction Inspector
City of Burlington
289-983-6304
The City of Burlington and Halton Region will be continuing improvements in the Bromley Road area in 2024, 2025, 2026 and 2027.
Construction Schedule
Spring 2024 to May 2027
Halton Region will be replacing the existing watermain, wastewater main and services. City work includes the construction of new sidewalk, replacement of existing curb, sidewalk, roadway asphalt, street lighting upgrades on the streets per the location map.
D’Orazio Infrastructure Group Ltd. has been awarded the Bromley Road Area Minor Reconstruction contract.
Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.
The City of Burlington and Halton Region will be working on:
| Location | City Works | Region Works |
|
Bromley Road Verhoeven Road Broughton Crescent Linwood Drive Maureen Court Brewer Court |
|
|
This project’s scope includes the replacement of both the water and wastewater systems, storm repairs and replacements, full curb, sidewalk, and asphalt replacement, sidewalk infill, and street lighting renewal.
Works will be completed in phases, making the work on each street and area not continuous.
Multiple phases of excavation along each street are required to complete the works.
There will be time in between each operation when work will be paused on your street while the Contactor works on a different task or street. We ask that residents continue to be patient and understanding. Every effort will be made to expeditiously complete the works on each street.
Note that the storm sewer replacement scope has been expanded on the project due to the in-situ condition encountered, as well as the extension of Regional work timelines. This will possibly extend the overall project schedule.
Project schedule
Below is the current schedule of remaining works.
| Location | Works | Timeline |
|---|---|---|
|
Bromley Rd. - Linwood Cr. to White Pines Dr. Maureen Ct., Linwood Cr. |
Topsoil and sod |
Spring 2026 |
|
Wastewater lateral lining |
Summer 2026 |
|
|
Bromley Rd. – White Pines Dr. to Kenwood Ave. |
Storm sewer works |
Spring 2026 |
|
Curb, sidewalk, and base asphalt |
Summer/Fall 2026 |
|
|
Broughton Cr., Brewer Ct. Verhoven Rd. |
Watermain installation and servicing Storm sewer works |
Spring/Summer 2026 |
|
Street lighting |
Summer 2026 |
|
|
Curb, sidewalk, and base asphalt |
Summer/Fall 2026 |
|
|
All Streets |
Top asphalt |
Spring 2027 |
The construction timeline above is tentative and dependent on weather and other factors.
The major construction activities associated with this project are nearing completion, and we remain focused on bringing the project to a successful conclusion. Base asphalt, driveway restoration, and sod placement will be completed by November 2026 for all streets. The final adjustments to catch basins and maintenance holes, including the top layer of asphalt paving, are scheduled for completion in May 2027.
2026 leaf collection schedule and winter maintenance will not be disrupted.
The following information may be helpful if you are concerned about a construction project in your neighbourhood.
During normal construction hours (Monday to Friday, 7 a.m. to 6:30 p.m.) vehicle access to and from your properties may be difficult. Driveways will be temporarily closed when work is being carried out in the immediate area. Either the inspector or the contractor will notify you of access interruptions before the closure.
During replacement of existing curb and sidewalk, and the installation of services and laterals, portions of existing driveways will require replacement. These driveways will be replaced full width to the limit of disturbance.
For information regarding a driveway restoration credit being paid to residents for the funding of privately contracted restoration of the entire driveway in-lieu of the partial driveway restoration under the contract, i.e. up to the limit of disturbance due to construction only, please contact Hasan.Rabby@burlington.ca.
Leaf Collection - November 24 - 28, 2025
Due to the ongoing construction, the City is unable to complete regular loose-leaf collection on all streets within the project limits. As a part of this project, the loose-leaf collection will be completed by the Contractor from November 24 - 28, 2025. Any efforts made by residents to bag leaves and place at the curbside is appreciated.
Residents are asked to bag or accumulate leaves and keep them at the roadside for pick-up.
For the duration of construction, enforcement of the “5-hour” maximum on-street parking by-law will be relaxed when your driveway is inaccessible or closed. Residents are asked to register their vehicle online or call 905-335-7816 Monday to Friday 8:30 to 4:30 p.m.
Vehicles are not permitted to park where signs are posted. (e.g. No Parking, No Stopping, and Fire Route etc.) In addition, vehicles are not to block fire hydrants, driveway access or park their vehicles facing the wrong direction.
How does a parking exemption work?
During City construction projects, the extra days will not be included in the 15-day-per-year limit when your driveway is not accessible. However, it is important to register your vehicle for this program so that you will not receive a parking ticket.
OZA Inspections Ltd. has been hired by our contractor to complete internal and external condition surveys of the residences within the project limits. The purpose of these inspections is to photograph and note the condition of the existing structure, i.e. cracking or displacement in walls, plaster, floors, patios, etc. This is to protect both the homeowners and the contractor in the case of any damage, actual or purported caused by construction, though damage this is very rare and unlikely. An OZA representative will be coming to your home to schedule the survey. Note that these inspections, internal and/or external, are free and completely optional, at the discretion of the homeowner.
Road closures/lane restrictions
Tree protection barriers will be erected around all trees in the right-of-way and in front of adjacent private trees within the construction limits, with an opening to allow homeowner access to maintain the area within.
There may be boulevard trees removed due to conflict with the installation of the new water and wastewater mains and services, as well as other unforeseen circumstances. If a conflict arises, alternate installation locations and methods will be reviewed in depth, but tree removals may be unavoidable. Homeowners adjacent to these removals will be informed prior to removal.
Utilities, such as Union Gas, Hydro and Bell Canada, have already started to locate their existing infrastructure to prepare for this construction. Residents will see various coloured paint marks and flags on their lawn and roadway. These are noting the location of various underground utilities, i.e. gas (yellow), hydro (red) water (blue), etc. Please do not remove these marker stakes or paint markings. Staff will return to remove them once the project is complete.
The contractor may ask you to restrict your water usage at specific times during the course of construction. This will last for a limited amount of time while they rehabilitate and/or replace your lateral.
Water and wastewater disruptions
There will be disruption to your water service during the course of the project. Halton Region will provide at least 48 hours advance written notice of all scheduled shutdowns or disruptions.
Watermain installation and tie-in work may be required to take place at night. Advance notification will be provided.
Winter construction and maintenance
Construction work will continue throughout the winter months. As part of this project, the Contractor will complete regular winter maintenance within the project limits.
You may at times experience minor vibration from construction equipment. We recommend that you remove small, light objects from shelving around the house.
Updates will be posted throughout the project.
Contact Us
City of Burlington
426 Brant St., PO Box 5013,
Burlington, ON L7R 3Z6
Phone: 905-335-7777
Toll Free: 1-877-213-3609
Email: city@burlington.ca
This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.