• April - May 2023
The City of Burlington and Halton Region will be continuing improvements in the Rexway Drive area in 2023. This will include full watermain and water service replacement (Region) and complete curb, sidewalk, and asphalt replacement (City) on the streets per the map below.
Check this webpage for updates throughout the project. If you'd like to subscribe to be emailed a notification when the page is updated, please see the top right corner of this page.
The remaining project works in the Rexway Drive Area Minor Reconstruction - Phase 2 are scheduled to begin in April 2023 and are tentatively scheduled to be completed by the end of May 2023.
|
Location |
City Works |
|
Stage 1 – Woodview Drive, Rockwood Drive and Chestnut Place |
|
|
Stage 2 - Ronald Dr., Manfred, Dr., Putter Pl., Jennifer Cr., |
|
|
Stage 2 - Thornwood Ave., Geneva Park Dr., Geneva Pl., Windsor Ct., Breamore Pl., Braemore Rd. |
|
The City of Burlington and Halton Region will be working on:
|
Location |
City Works |
Region Works |
|
Stage 1 Works: |
||
|
Rockwood Drive Woodview Drive Chestnut Place |
|
|
|
Stage 2 Works: |
||
|
Ronald Drive Manfred Drive Geneva Park Drive |
|
|
|
Jennifer Crescent Thornwood Avenue |
|
|
|
Putter Place, Windsor Court, Geneva Place, Braemore Place |
|
|
|
Braemore Road |
|
|
| Day-to-day construction |
|
Bart Barnes, Construction Inspector City of Burlington 905-220-5493 bart.barnes@burlington.ca |
| Watermain and service replacement |
|
Chandni Desai, Project Manager III Halton Region 905-825-6000, ext. 3235 chandni.desai@halton.ca |
| All other construction inquiries |
|
Ryan Stoneman, Project Manager City of Burlington 905-335-7600, ext. 7818 ryan.stoneman@burlington.ca |
Lane restrictions and short-term, localized road closures will be in place during construction. You will still have access to your home. For more information, please see the Information for Homeowners section below.
The following information may be helpful if you are concerned about a construction project in your neighbourhood.
| Parking |
|
During normal construction hours, Monday to Friday, 7 a.m. to 5:30 p.m., vehicle access to and from your property may be difficult. Driveways may be temporarily closed when work is being carried out in the immediate area. When your driveway is inaccessible or closed, please park on a neighbouring street, or where no construction is taking place. If your vehicle will be in contradiction to the below by-law, register your vehicle for the On-Street Parking Exemption Program. How does a parking exemption work? It allows a vehicle to park on the street beyond the 5-hour limit or overnight between 1 a.m. to 6 a.m., up to 15 days per calendar year, per license plate. The only two parking offences waived AFTER a vehicle is registered for a parking exemption are:
All other parking offences apply as they are not part of the parking exemption program. If you have any questions about parking, please contact Parking Services at 905-335-7816. |
| Garbage pickup |
| Please continue to put your garbage and recycling out on the usual day. It is the contractor's responsibility to move your garbage to a location that can be easily picked up by the garbage truck and return your garbage containers. To help the contractor return your bins to you, we ask that you write your house number on your garbage cans, recycling bins and green carts. |
| Access to your home |
|
During normal construction hours, Monday to Friday, 7 a.m. to 5:30 p.m., vehicle access to and from your property may be difficult, and driveways may be temporarily closed when work is being carried out in the immediate area. The inspector or contractor will notify you of this before the closure. |
| Water services |
|
There will be interruptions to your water service during construction while completing watermain tie-ins and when transferring the houses to the new watermain. Halton Region will provide 48 hours advanced notice of all scheduled service interruptions. Some watermain installation and tie-in work may be required to take place at night. |
| Vibration |
| There may be times when you feel some minor vibrations from construction equipment. We recommend that you remove small, light objects from shelving around the house to prevent damage. |
| Lawn irrigation system |
| If you have a lawn irrigation system, we recommend that you disconnect and remove any sprinkler heads within the city's road allowance. The city inspector will notify you if your system is affected. |
| Road closures/lane restrictions |
| Lane restrictions and short-term road closures will be in place during construction. You will still have access to your home. Additional information will be provided during construction. |
|
Pre-condition survey |
| dBA Services Inc. will be reaching out to homeowners within the construction limits to provide an exterior condition survey. This is an optional service being provided to the residents on this project. |
| Driveway restoration |
|
Under the contract, asphalt/concrete driveways adjacent to new curb and sidewalk, or that contain water service shutoffs, will be restored from the limit of disturbance to the curb line at the roadway. Option A
Option B
If Option B is your preference, please contact Hasan Rabby at hasan.rabby@burlington.ca by July 31, 2022. |
Updates will be posted throughout the project.
For more information about this project, contact:
Ryan Stoneman
Project Manager
Engineering Services, City of Burlington
905-335-7600, ext. 7818
ryan.stoneman@burlington.ca