The City of Burlington and Halton Region will be continuing improvements in the Autumn Hill Crescent area and on Palmer Drive in 2022 and 2023.
This will include curb, sidewalk, and asphalt replacement, street lighting upgrades (City of Burlington), and full watermain and water service replacement (Region of Halton) on the streets per the map below. Please note that A Cosmos Concrete & Paving Ltd. is the only driveway paving company hired by the general contractor King Paving & Construction Ltd. for this project. There is no other driveway paving company associated with this project.
The remaining project works in the Autumn Hill area are scheduled to begin in March 2023. Resident should expect to see the Contractor mobilize during the week of Mar. 20, 2023, including survey work, construction signage and barrel setup, and active construction as early as the week of Mar. 27, 2023. This timeline has the potential to be affected by weather. Construction is currently scheduled to be complete by the end of May 2023.
| Location | City Works |
|---|---|
|
Autumn Hill Cr. - Driftwood Dr. to Snowhill Ct. Driftwood Dr. - Autumn Hill Cr. to Hemlock Ct. Driftwood Dr. – Autumn Hill Cr. to dead-end |
|
|
Carncastle Gt., Flanagan Ct. Parknoll Ct., Fontana Ct. |
|
| Day-to-day construction |
|
Tom Georgiadis Construction InspectorCity of Burlington 905-220-1693 tom.georgiadis@burlington.ca |
| Watermain and service replacement |
|
Gurpreet Chaggar Project Manager IIHalton Region 905-825-6000, ext. 3059 gurpreet.chaggar@halton.ca |
| All other construction inquiries |
|
Ryan Stoneman Project ManagerCity of Burlington 905-335-7777, ext. 7818 ryan.stoneman@burlington.ca |
The following information may be helpful If you are concerned about a construction project in your neighbourhood.
Updates will be posted throughout the project.
| Project updates |
|
Palmer Drive – Guelph Ln. to Michael Cr. |
|
City of Burlington
Region of Halton
|
| Palmer Drive – Michael Cr. to Centennial Dr. |
|
City of Burlington
Region of Halton
|
|
Autumn Hill Cr. – Driftwood Dr. to Snowhill Ct. |
|
City of Burlington
Region of Halton
|
|
Driftwood Dr. – Autumn Hill Cr. to Hemlock Ct. |
|
City of Burlington
Region of Halton
|
| Carncastle Gt. |
|
City of Burlington
|
|
Flanagan Ct. |
|
City of Burlington
|
|
Parknoll Ct. |
|
City of Burlington
|
|
Fontana Ct. |
|
City of Burlington
|
|
Driftwood Dr. – Autumn Hill Cr. to dead-end |
|
City of Burlington
|
| Driftwood Dr. - Hemlock Ct. to Autumn Hill Cr. |
|
City of Burlington
|
|
Autumn Hill Cr. - Snowhill Ct. to Driftwood Dr. |
|
City of Burlington
|
|
Hemlock Ct. |
|
City of Burlington
|
|
Snowhill Ct. |
|
City of Burlington
|