Walkers Line culvert, south of Britannia - July to October 2025
Britannia Road culvert, west of Walkers Line - July to October 2026
The City of Burlington will be replacing two existing stormwater culverts on Walkers Line (south of Britannia Road) and Britannia Road (west of Walkers Line).
The Walkers Line culvert will be replaced during the summer 2025. The work will include the removal of the existing corrugated steel pipe culvert and replacement with a concrete box culvert system. As part of this project, roadway improvements will be made including localized roadway repaving and steel beam guiderail installation.
The Britannia Road culvert west of Walkers Line will also be replaced in 2026. The structure is approaching the end of its service life and is recommended for replacement. The City will be replacing the existing rigid frame culvert with a concrete box culvert system.
During construction activities full road closures are anticipated. Signed detour routes will be installed ahead of construction and provide an alternative route around the construction area.
Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.
| Location | Scope | Tentative schedule |
|---|---|---|
|
Walkers Line Culvert, south of Britannia |
|
July to October 2025 |
|
Britannia Rd, 750 metres west of Walkers Line. |
|
July to October 2026 |
Note: The construction schedule outlined is tentative. Additional information will be provided once the contract has been awarded and schedule confirmed.
|
Walkers Line, 90 meters south of Britannia Road |
|
A full road closure is needed to install the culvert on Walkers Line. Vehicle traffic will be able to follow the designated detour route using Britannia Road, Appleby Line, and Side Road No.2. Signage will be installed in advance of the construction work. Once the culvert installation is complete including road resurfacing work, the Walkers Line project area will be re-opened to the public. View the Walkers Line culvert proposed detour plan (PDF)
|
|
Britannia Rd, 750 meters west of Walkers Line |
|
Starting in July 2026, a full road closure will be installed on Britannia Road, west of Walkers Line to allow for construction of the proposed culvert. Vehicle traffic will be able to follow the designated detour route using Britannia Road, Guelph Line, and Derry Road. View the Britannia Road culvert proposed detour plan (PDF)
|
| Day-to-day construction |
|
Eric Canham, Construction Inspector City of Burlington 905-335-7600, ext. 7783 |
| All other construction inquiries |
|
Chris Onishi, Project Manager City of Burlington 905-335-7600, ext. 7682 Nathan Youngs, Contract Administrator City of Burlington 289-208-2468 |
The following information may be helpful If you are concerned about a construction project in your neighbourhood.
Updates will be posted throughout the project.