The City of Burlington and the Region of Halton are completing a Minor Reconstruction Project in the Prospect Street Area starting in the winter of 2024 and finishing in December 2026. The City and the Region have split the Prospect Street Area project into two phases, which shall be detailed below.
Phase One of the Prospect Street Area Minor Reconstruction Project was awarded to KAPP Infrastructure Inc in October 2024. Construction started on Phase One of the Prospect Street project in December 2024 with watermain installation from Guelph Line to Cumberland Ave.
The underground construction continued on Prospect Street from Ashley Avenue to Guelph Line in 2025 and was fully completed by November 2025.
In 2026, the City of Burlington and the Region of Halton will be completing surface restoration works on Prospect Street from Ashley Avenue to Cumberland Avenue as well as completing resurfacing work on Dynes Road from Prospect Street to New Street, and the full length of Regency Court.
For more information on the scope of work and project schedule, please see the Prospect Street Phase One table below.
Phase Two of the Prospect Street Area Minor Reconstruction Project was awarded to Amico Infrastructures Inc. in March 2025.
Construction of the 2nd Phase of the Prospect Street Project began in June 2025, with watermain and waste watermain being installed from George Street to Brant Street. The majority of the underground construction work on Prospect Street and Grahams Lane was completed by December 2025.
In 2026, the City of Burlington and the Region of Halton will be completing the surface restoration of Prospect Street and Grahams Lane. In addition, we will be completing the reconstruction of Legion Road and the resurfacing of Maplewood Drive.
For more information of the scope of work and project schedule, please see the Prospect Street Phase Two table below.
Check this webpage for ongoing project updates. If you wish to receive email notifications whenever the project page is updated, use the button located at the bottom right corner of this page, beneath the Contact Us details. To stay informed about all current city construction projects and other municipal news, please subscribe using the button positioned at the top right corner of this page.
Please see below for the outstanding work to be completed:
| Location | City Works | Expected Timeline |
|---|---|---|
|
Prospect Street (Ashley Avenue to Guelph Line) |
|
Spring/Early Summer 2026 |
|
Prospect Street (Guelph Line to Cumberland Avenue) |
|
Spring/Early Summer 2026 |
|
Dynes Road |
|
Summer 2026 |
|
Regency Court |
|
Spring/Early Summer 2026 |
|
South Service Road (Billings Court to Harvester Road) |
|
Fall 2026 |
|
Fraser Drive |
|
Fall 2026 |
Note: The construction schedule outlined is tentative. Delays and schedule changes may occur throughout the course of the project.
The City of Burlington and The Region of Halton will be working on:
| Location | City Works | Expected Timeline |
|---|---|---|
|
Prospect Street and Graham’s Lane (Grahams Lane to Joyce Street) |
|
Summer 2026 |
|
Legion Road |
|
Early Summer 2026 |
|
Maplewood Drive |
|
Early Summer 2026 |
| Day to day construction inquiries for Phase One (Cumberland Ave to Ashley Ave) |
|
David Hill Site Inspector, Design and Construction 289-983-5003 |
|
Day to day construction inquiries for Phase Two (Joyce St to Grahams Ln) |
|
Tom Georgiadis Site Inspector, Design and Construction 905-220-1693 |
| Road construction and restoration inquires |
|
Nathan Youngs Contract Administrator of Design and Construction 905-335-7600, ext.7567 |
| All watermain and waste watermain inquires |
|
Vivek Nemani Project Manager, Region of Halton 905-825-6000, ext. 7617 |
| All other construction inquires |
|
Rob Stuart Project Manager 905-335-7600, ext. 7519 |
The following information may be helpful If you are concerned about a construction project in your neighbourhood.
Lane restrictions and a rolling road closures will be in place during construction during watermain and waste watermain construction. Local residents will still have access to their homes.
• Phase One from Ashley Avenue to Guelph Line
• Phase Two from Brant Street to Joyce Street
| Road closures |
|
Lane restrictions and a rolling road closures will be in place during construction during watermain and waste watermain construction. Local residents will still have access to their homes. Once a Contractor has been hired and a tentative construction schedule finalized, additional information will be provided to the public. |
| Parking |
|
During construction, the five-hour maximum limit for street parking will not apply when your driveway is inaccessible or closed. In this situation, please park on neighboring streets, where there is no construction. Please do not:
Please obey all parking regulations to make sure you don't receive a ticket. For more information about parking, visit our parking page. |
| Garbage pickup |
|
Please continue to put your garbage and recycling out on the usual day. It is the contractor's responsibility to move your garbage to a location that can be easily picked up by the garbage truck and return your garbage containers. To help the contractor return your bins to you, we ask that you write your house number on your garbage cans, recycling bins and green carts. |
| Access to your home |
|
During normal construction hours, Monday to Friday, 7 a.m. to 5:30 p.m., vehicle access to and from your property may be difficult, and driveways may be temporarily closed when work is being carried out in the immediate area. The inspector or contractor will notify you of this before the closure. |
| Vibration |
|
There may be times when you feel some minor vibrations from construction equipment. We recommend that you remove small, light objects from shelving around the house to prevent damage. |
| Lawn irrigation system |
|
If you have a lawn irrigation system, we recommend that you disconnect and remove any sprinkler heads within the city's road allowance. The city inspector will notify you if your system is affected. |
Updates will be posted throughout the project
| Project updates |
|